• Downtown Construction Update

  • Update from Delta 3:

    Below is an update as to what has happened recently on-site and what is planned to happen over the next two weeks:

     

    Schedule Change:

    • No change

     

    Traffic Control:

    • Parisi will be working on the concrete portions of High Street, specifically on the blocks between Commerce Street / Vine Street and Henry Street / Chestnut Street.  Commerce Street / Vine Street block is anticipated to be closed to all traffic from Monday 8/21 – Friday 8/25.  Henry Street / Chestnut Street block is anticipated to be closed to all traffic Monday 8/21 – Tuesday 8/22 and limited but open to through traffic Wednesday 8/23 – Friday 8/25.

     

    Erosion Control:

    • All erosion control has been removed and areas of disturbance have been stabilized.

     

    Contractor’s Schedule (items started/completed):

    • Light poles on Jail Alley, Commerce Street, and High Street (Commerce Street – Chestnut Street) are installed.

     

    Contractor’s Schedule (two-week outlook):

    • Week of August 21st
      • AB Electric is to complete installation of light poles.
      • Parisi is anticipating to complete remaining punch list items.
      • Parisi will be doing final finishing to the concrete pavement.  Please follow all traffic control to ensure Parisi’s work can be completed in a timely manner.
    • Week of August 28th
      • No work anticipated

     

    Miscellaneous:

    • The Mineral Point Chamber of Commerce will be hosting a Historic Downtown Reconstruction Grand Opening of Saturday August 26th with a ribbon cutting at 4 pm.